CEDAR BAYOU UPDATE – JULY 27, 2014

Photos: Lisa Laskowski

As of 7/27/2014, RLB’s progress in both Cedar Bayou and Vinson Slough continues with a total volume removed to date of approximately 330,000 cubic yards of material, including the spoil pile excavation. Dredging has continued in Cedar Bayou with approximately 3,400 feet of total advance since the start of the project. The contractor continues to maintain the silt curtains around the active dredging area to protect nearby aquatic resources as the dredge advances.

Click here to view the weekly progress report from Coast & Harbor Engineering.

We want to remind our members and general public that the Cedar Bayou Construction area is a designated work zone and requires permission for entry.

As always, we appreciate everyone’s support for this important project!!

CEDAR BAYOU UPDATE – JULY 20, 2014

Photo: Coast & Harbor Engineering

As of 7/20/2014, RLB’s progress in both Cedar Bayou and Vinson Slough continues with a total volume removed to date of approximately 302,000 cubic yards of material, including the spoil pile excavation.

Dredging has continued in Cedar Bayou with approximately 3,200 feet of total advance since the start of the project. The contractor continues to maintain the silt curtains around the active dredging area to protect nearby aquatic resources as the dredge advances.

Click here to view the weekly progress report from Coast & Harbor Engineering.

We want to remind our members and the general public that the Cedar Bayou Construction area is a designated work zone and requires permission for entry.

CEDAR BAYOU UPDATE – JULY 13, 2014

Photos: Ellie and Ed Block, Commissioner Betty Stiles, and Judge Mills

Below are aerial photos of Cedar Bayou from the past few weeks. As of 7/13/2014, RLB’s progress in both Cedar Bayou and Vinson Slough continues with a total volume removed to date of approximately 290,000 cubic yards of material, including the spoil pile excavation. Dredging has continued in Cedar Bayou with approximately 3,100 feet of total advance since the start of the project. The contractor continues to maintain the silt curtains around the active dredging area to protect nearby aquatic resources as the dredge advances.

Click Here to view the weekly progress report from Coast & Harbor Engineering.

We want to remind our members and general public that the Cedar Bayou Construction area is a designated work zone and requires permission for entry.

As always, we appreciate everyone’s support for this important project!!

CEDAR BAYOU UPDATE – JULY 6, 2014

Photo: Coast & Harbor Engineering

As of 7/6/2014, RLB’s progress in both Cedar Bayou and Vinson Slough continues with a total volume removed to date of approximately 223,000 cubic yards of material, including the spoil pile excavation.

Dredging has continued in Cedar Bayou with approximately 2,900 feet of total advance since the start of the project. The contractor continues to maintain the silt curtains around the active dredging area to protect nearby aquatic resources as the dredge advances. Figure 1 shows the hydraulic working on the western half of the design template.

Click Here to view the weekly progress report from Coast & Harbor Engineering.

We want to remind our members and the general public that the Cedar Bayou Construction area is a designated work zone and requires permission for entry.