Photo by: Lisa Laskowski
As of 10/5/2014, RLB’s progress in both Cedar Bayou and Vinson Slough is complete with a total volume removed to date of approximately 555,000 cubic yards of material, including the spoil pile excavation.
RLB has completed moving all construction equipment offsite as of 10/05 and continues to conduct post-construction surveys.
Click Here to view the weekly progress report from Coast & Harbor Engineering.